SBI Clerk Exam 19 Nov 2022 Shift 1 Solved Paper

© examsiri.com
Question : 37 of 100
 
Marks: +1, -0
A certain work was completed by A in 9 days, B in 12 days, C in 15 days, If A and C did work for 4 days and then leftt, then B will finishes rest work in how many days?