Question : 41 of 100
 
Marks: +1, -0
P can do a piece of work in 60 days & Q can do the same work in 50 days. Find the ratio of working efficiencies of P and Q.
A. 1 : 3
B. 6 : 5
C. 5 : 6
D. 4 : 5