Question : 99 of 100
 
Marks: +1, -0
17 trainees can do as much work as 4 experts can do in a day. It takes 12 experts and 9 trainees 5 days to dig a pond. How many trainees will one need alongside 4 experts to dig a similar pool in 15 days ?