Question : 29 of 75
Marks:
+1,
-0
Thirty men can do a piece of work in 16 days working 8 hrs a day. How many men are needed to complete another work, which is twice the first one, in 10 days working 12 hrs a day?
The following are the steps involved in solving the above problem. Arrange them in sequential order.
A) M2 =
B)
C)
D) M2 = 64
The following are the steps involved in solving the above problem. Arrange them in sequential order.
A) M2 =
B)
C)
D) M2 = 64