Directions (15-17): Study the information and answer the questions.
Vijit is a government contractor, who got a contract for the construction of multi-speciality hospital in 25 months. After the completion of 60% of work, he takes the help of Mridul and Parul.
Mridul is 50% as efficient as Vijit and Parul is 50% as efficient as Mridual.
Vijit is a government contractor, who got a contract for the construction of multi-speciality hospital in 25 months. After the completion of 60% of work, he takes the help of Mridul and Parul.
Mridul is 50% as efficient as Vijit and Parul is 50% as efficient as Mridual.
© examsiri.com
Question : 17 of 65
Marks:
+1,
-0
Find the time taken by all of them to finish the remaining work.