Question : 47 of 72
Marks:
+1,
-0
Project Manager John and his team have finished creating the Work Breakdown Structure (WBS) and Work Breakdown Structure dictionary. Then, he prepares a detailed and itemized documentation of all of the schedule activities that are part of the project. What should he do NEXT?