You are a Project Manager. You need to decide whether to buy insurance for a temporary manufacturing facility. The likelihood of a mishap is assessed at 10% and the likely impact is evaluated at $500,000. The cost of insuring is $20,000 and has a $10,000 deductible. Would you buy insurance?