PMP Certification Practice Test 6

© examsiri.com
Question : 48 of 72
 
Marks: +1, -0
Dax’s project is to build a new bridge over a small creek. The government leaders want the bridge to be completed as soon as possible because of the economic impact the construction will have on the businesses in the community. An environmental group, however, has concerns that the bridge will disrupt the nature and ecological factors surrounding the creek. The environmental group is demanding additional testing, surveys, and analysis before the project can continue. The environmental group is which one of the following in this instance?