Question : 4 of 72
 
Marks: +1, -0
You are the project manager for a company that completes projects for other organizations. Your company has no formal archiving process for project records. Your project has just completed and the customer has formally accepted the project work. The customer is very pleased with the project and is considering hiring your organization for another project. What should you do with your current documentation?