PMP Certification Practice Test 6
© examsiri.com
Question : 33 of 72
Marks:
+1,
-0
You are managing a complex, critical project and have put in a lot of effort to make the team technically proficient during the process. The project is in the final acceptance testing stage when a senior resource, Janice, comes to discuss her plans of continuing her education and leaving this current assignment. She would require a positive recommendation for work from you to fulfill admission requirements. What should you do?
Go to Question: