PMP Certification Practice Test 6
© examsiri.com
Question : 22 of 72
Marks:
+1,
-0
You are the Project Manager of a project to install new light fixtures throughout several factories. The project is expected to last one year and has a BAC of $750,000. The project is now in month four and has a CPI of .89. Which one of the following statements is true about this project?
Go to Question: