PMP Certification Practice Test 4

© examsiri.com
Question : 72 of 72
 
Marks: +1, -0
You are managing a critical project with frequent changes in requirements. You are in the testing phase of the project, and the customer has requested an additional new feature. You have assessed the impact of the change on the triple constraints with your team. What should be your NEXT step?