Question : 70 of 72
Marks:
+1,
-0
A global scale software application project includes multiple risks. These include :
A 30 percent probability of a 15 day delay in the coding process
A 40 percent probability of a 10 day delay in the user interface design process
A 10 percent probability of a 20 day delay in the online integration
What would be the EMV ( Expected Monetary Value) of the project?