PMP Certification Practice Test 3
© examsiri.com
Question : 68 of 72
Marks:
+1,
-0
While working as a project manager for a leading Technology consulting firm, you were involved in a project which had a budget of $93000 with a duration of 1.5 months. You have currently spent $35000 to complete the work which was originally expected to cost $39000. As per your schedule, you should have spent $40,000 by this time. How would you describe your project ?