PMP Certification Practice Test 3

© examsiri.com
Question : 66 of 72
 
Marks: +1, -0
As a Project Manager, you need to estimate the regression testing for your product. You would like to do 5 full testing cycles. Each cycle is estimated to take 4 days. What is your estimated duration for the testing activity?