Question : 56 of 72
Marks:
+1,
-0
A Project Manager is planning a project, and he is creating a plan to describe how human resource requirements in the project would be met. He is using a bar chart tool called a Resource Histogram for charting this requirement. However, he notices that some of the individual bars in the Resource Histogram extend beyond the maximum allowed hours. What should the Project Manager do to correct it?