Question : 39 of 72
Marks:
+1,
-0
You have just taken over a project that is several months late and is in very bad shape. The previous project manager had not kept accurate records on the project work, project expenses, or the overall performance of the project. The customer is still very interested in having the project completed and is not holding you responsible for the project work up to this point. Of the following, which one is the best solution to move forward and to create accurate records of your progress?