Question : 35 of 72
 
Marks: +1, -0
As a Project Manager you are estimating the duration of your project activities using PERT technique (Program Evaluation and Review technique). For a particular project activity, your optimistic estimate is 41 days, pessimistic estimate is 89 days, and most Likely estimate is 60 days. What would be the expected duration and range of the estimate for this activity?