You are not satisfied with the way John is handling a project. Given the urgent circumstances, You reassign the work to Vanessa to ensure the deadlines are met and the deliverables are completed as per the defined scope. You ask the newly Vanessa to get all the information regarding the project from Alex. However, being angry and upset over having the project work taken away from them, Alex refuses to share the information with Vanessa, making it impossible for her to start work on the project without having the necessary information to proceed. The deadline is approaching fast, What two powers can you use in this case to make sure the project deadlines are met.