A project manager is working on a project that involves setting up telecommunication towers on a mountainous area. There is a 40 percent chance of a delay in engineering , causing an impact of $300,000 and the delays due to weather may cause an impact of $150,000 (with a probability of 50 percent). What should be the value of the reserves ?