The research and development (R&D) team has been working on developing a new software product for nine months and feel the product is now ready for release to the market and for final handover to the operations team. The operations manager asks the operations team to do a quick test and report the findings. The report highlights that there are many changes to this new product's interface of which the operations team was not aware. This will require new training.
What should the project manager have done?
What should the project manager have done?