Question : 38 of 45
Marks:
+1,
-0
After preparing the work breakdown structure (WBS), the project manager is ready to assign task areas to project team members. Subsequently, the project sponsor asks to add requirements that the team feels are unachievable.
What should the project manager do next?
What should the project manager do next?