PMP Certification Planning Questions Test 4

© examsiri.com
Question : 36 of 45
 
Marks: +1, -0
While estimating project costs, a project manager works with a subject matter expert (SME) who has historically underestimated the effort necessary to deliver project requirements. In all other areas, however, the SME is a good contributor, well respected, and often requested by stakeholders.
To proactively mitigate the risk of underestimation, what should the project manager do?
Go to Question: