Question : 36 of 45
Marks:
+1,
-0
While estimating project costs, a project manager works with a subject matter expert (SME) who has historically underestimated the effort necessary to deliver project requirements. In all other areas, however, the SME is a good contributor, well respected, and often requested by stakeholders.
To proactively mitigate the risk of underestimation, what should the project manager do?
To proactively mitigate the risk of underestimation, what should the project manager do?