PMP Certification Planning Questions Test 4
© examsiri.com
Question : 1 of 45
Marks:
+1,
-0
A project manager is working with a new quality manager to finalize the quality management plan. The quality manager suggests an expensive quality tool with which the project manager is unfamiliar. The project manager says there is a cheaper alternative, but the quality manager is adamant that there is not. To maintain the current schedule, the quality management plan and associated procurement must be completed the following week.
What should the project manager do next?
What should the project manager do next?