A customer asks the project manager to deliver a project in 60 days that was previously scheduled for delivery in 90 days. No activities can be performed in parallel.
The requested change is approved by the change control board (CCB).
What should the project manager do to fulfill this request?
The requested change is approved by the change control board (CCB).
What should the project manager do to fulfill this request?