PMP Certification Planning Questions Test 3
© examsiri.com
Question : 46 of 70
Marks:
+1,
-0
A project's initial budget is US200,000, but its actual cost (AC) to date is US160,000. During an evaluation of the project's progress, the project manager determines that the cost performance index (CPI) is 0.8, which exceeds the budget baseline.
If current performance is maintained, what is the estimate to complete (ETC)?
If current performance is maintained, what is the estimate to complete (ETC)?