Question : 44 of 70
 
Marks: +1, -0
Detailed design has begun on a firm fixed price (FFP) contract, and the statement of work (SOW) has been clearly defined for the consultants. Now, an expert communicates to the consultants that additional work is needed.
How should the project manager proceed?