While performing an earned value analysis (EVA), a project manager notices that the cost performance index (CPI) is not what was expected.
The project manager investigates and is unable to locate purchase orders or receipts for items used in the project.
What should have been used to prevent this from occurring?
The project manager investigates and is unable to locate purchase orders or receipts for items used in the project.
What should have been used to prevent this from occurring?