PMP Certification Planning Questions Test 3
© examsiri.com
Question : 28 of 70
Marks:
+1,
-0
During a project to create an organizational business plan, the project manager facilitates a strengths, weaknesses, opportunities, and threats (SWOT) analysis workshop with senior management. What process is the project manager implementing?