The table lists project activities, with activities A and H as start and end activities.
What is the project's critical path?
What is the project's critical path?
| Activity | Duration | Dependency |
| A | 2 | - |
| B | 3 | A |
| C | 4 | A |
| D | 4 | B&C |
| E | 5 | B |
| F | 3 | C |
| G | 2 | D&F |
| H | 2 | E&G |