Question : 64 of 70
 
Marks: +1, -0
During planning, a project team documented the possibility that new hardware could arrive up to 45 days late and delay the project's delivery date. One month into the project, the manufacturer notifies the project manager that the hardware will be shipped 20 days sooner than anticipated.
What should the project manager do next?