A project has five finish-to-start (FS) activities.
Activity A takes one day
Activity B follows A and takes five days
Activity C follows B and takes two days.
Activity D follows B and A takes two days.
Activity E is preceded by C and D and takes two days.
What would be the critical path(s)?