PMP Certification Planning Questions Test 2

© examsiri.com
Question : 25 of 70
 
Marks: +1, -0
A project has a budget of US$900. Its estimate to complete (ETC) is US$600, the budget at completion (BAC) is $US800, and the estimate at completion (EAC) is US$1,200.
What is the management reserve?
Go to Question: