| Activity | Probability of Occurrence | Cost |
| A | 20% | US 100,000 |
| B | 50% | US 300,000 |
| C | 70% | US 50,000 |
| D | 55% | US 250,000 |
Based on the table, what activity should receive risk-response-planning priority?