Question : 69 of 71
 
Marks: +1, -0
A project team member decides that engaging the customer on some alternative designs is unnecessary if all functionalities are delivered. The entire team decides to only engage the technical department on the best product design. After user acceptance testing, the customer complains about the selected design.
To ensure that the customer accepts the project deliverables, what should the project manager do?