PMP Certification Monitoring and Controlling Test 4

© examsiri.com
Question : 66 of 71
 
Marks: +1, -0
Without consulting the project manager, a functional manager removes key project resources in order to assign them operational tasks. Since these resources are now focused on operational tasks rather than deliverables, the deliverables run late.
What should the project manager do first?
Go to Question: