PMP Certification Monitoring and Controlling Test 4

© examsiri.com
Question : 58 of 71
 
Marks: +1, -0
A project's earned value (EV) report indicates that an activity's cost variance (CV) is -5,000 and its schedule variance (SV) is 1,000. What is the status of this activity?