PMP Certification Monitoring and Controlling Test 4

© examsiri.com
Question : 53 of 71
 
Marks: +1, -0
To ensure quality standards are met, a project manager hires an external resource to inspect the quality of the deliverables. The cost for this inspection can be classified under what cost category?