PMP Certification Monitoring and Controlling Test 4

© examsiri.com
Question : 28 of 71
 
Marks: +1, -0
During a fast-tracked project, outputs are required for production immediately. A new engineering team member submits quality testing to the project manager for approval, but the project manager rejects it.
What should the project manager do next?