Question : 16 of 71
Marks:
+1,
-0
A project is being audited, and the project manager receives numerous comments and questions from an unfamiliar person in the company. The project manager shares this information with team members, none of whom know this person. The project manager is unsure how to manage this situation.
What should the project manager do first?
What should the project manager do first?