PMP Certification Monitoring and Controlling Test 3
© examsiri.com
Question : 53 of 70
Marks:
+1,
-0
A project manager is using control charts to determine whether or not a process is stable or has predictable performance. The upper and lower control limits are determined by the customer. A set of 18 data points were recorded and eight consecutive data points were found to be above the mean.
What can the project manager conclude from this finding?
What can the project manager conclude from this finding?