PMP Certification Monitoring and Controlling Test 2

© examsiri.com
Question : 69 of 70
 
Marks: +1, -0
A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the: