Question : 59 of 70
 
Marks: +1, -0
The following chart contains information about the tasks in a project.
Based on the chart, what is the cost performance index (CPI) for Task 2?
TaskPVACEV
110,00010,00010,000
210,0008,00010,000
310,0008,0008,000
49,00012,00010,000
510,00012,00012,000
610,00010,00012,000
712,00012,00010,000
810,0008,0009,000
912,00010,00011,000