PMP Certification Monitoring and Controlling Test 2

© examsiri.com
Question : 37 of 70
 
Marks: +1, -0
A project manager learns that the sponsor has been discussing project progress with a team member. What document should the project manager reference before addressing this issue with the sponsor?