PMP Certification Monitoring and Controlling Test 2

© examsiri.com
Question : 28 of 70
 
Marks: +1, -0
A project sponsor constantly demands that a project is delivered as quickly as possible. The project manager identifies an issue that will delay the project by one week.
What should the project manager do?