Question : 16 of 70
 
Marks: +1, -0
A project manager is running a long-term project for a company that is increasing its infrastructure. In month 13 of the project, the client escalates an issue that an expected delivery from a contracted third-party vendor was not received. Upon investigation, the project manager discovers that the vendor was unaware of this.
Where should the project manager verify the delivery schedule?