PMP Certification Monitoring and Controlling Test 2

© examsiri.com
Question : 13 of 70
 
Marks: +1, -0
Faulty vendor-supplied parts must be returned and reordered. Based on previous experiences with this vendor, the project team had already identified this as a risk.
What should the project manager do to record this?