PMP Certification Monitoring and Controlling Test 1

© examsiri.com
Question : 50 of 70
 
Marks: +1, -0
A product is completed according to the project management plan, and team members are released to their functional areas. Upon receipt of the deliverables, a stakeholder realizes that the product cannot be accepted until a new set of requirements are included.
What should the project manager do next?