PMP Certification Monitoring and Controlling Test 1
© examsiri.com
Question : 18 of 70
Marks:
+1,
-0
A project's most recent status report indicates a schedule performance index (SPI) of 1.1 and a cost performance index (CPI) of 1.2. A key stakeholder then suggests a change to include a value-added feature that would not impact project schedule and cost. What should the project manager do next?