PMP Certification Monitoring and Controlling Test 1

© examsiri.com
Question : 15 of 70
 
Marks: +1, -0
In a control chart, three measurement points in a process are below the mean and within control limits. Four measurement points are above the mean and outside the control limits.
How is this process performing?